Our work
HC-One: Aberpennar Care Home
Refreshing the shared spaces of a care home while residents and staff stayed in place.
Overview
HC-One asked Chameleon Group, one of its approved fit-out contractors, to refurbish the public areas of Aberpennar Care Home in Mountain Ash.
Years of use had worn the corridor doors and handrails, and the toilets and communal spaces were dated. Over 12 weeks we refreshed the communal lounge, reading nook, corridors and toilets to HC-One’s design standards, using robust, easy-to-maintain materials suited to a busy care home.
The home stayed open throughout. As principal contractor, we planned the work with the home manager to keep disruption to residents and staff to a minimum, and finished on time and within budget.
Scope of work
- Strip-out and demolition in the toilet areas
- Carpentry and new cupboards
- New kitchenette and media walls
- Plastering and Artex work
- Plumbing and tiling
- New flooring
- Painting and decorating
- Electrical works
- Project and site management
Patrick and his team at Chameleon Group did an outstanding job at Aberpennar Care home undertaking a tricky refurbishment for HC-One in a live environment, great communication, standards and professionalism. Well done Chameleon Group.
Challenge & solution
The challenge
Working in a live care home
Refurbishing an occupied care home is very different from working in an empty building. For the full 12 weeks, Aberpennar remained home to its residents and a workplace for its staff, so their safety and wellbeing came first at every stage.
Working areas had to be clearly defined and kept separate, and the work had to be planned around the home’s daily routine rather than the other way round. The finishes also had to stand up to a busy care setting and be easy to keep clean and maintain.
Our solution
Planning the work around the residents
As principal contractor, we built the programme around both the trades and the day-to-day running of the home. Risk assessments, barriers and signage marked out each working area, and we agreed the sequence of work with the home manager, site manager, care staff and our own operatives.
Rather than treating disruption as a construction problem, we looked at how each stage would affect the people around it and planned accordingly. Site management oversaw quality and health and safety throughout. The work was finished on time and within budget, and the home manager was particularly pleased with the standard of our contractors and how little the works disturbed residents and staff.