Studio Lime
A new headquarters for an architectural practice, fitted out from CAT A in five weeks.
Overview
Studio Lime, an architectural practice, was moving into a larger space at The Crescent, Temple Back, and wanted an office that supported collaboration, gave them better rooms for meeting clients and felt like their own.
Having worked with us before, they appointed Chameleon Group as principal contractor. We took the space from CAT A to a finished office with open-plan and collaborative areas, meeting rooms and a kitchenette, managing every trade involved.
Although extra works were added during the programme, the five-week project was completed on time and within budget. Large-scale Studio Lime branding is now a focal point of the interior.
Scope of work
- Asbestos management
- Partitions, glazed partitions, and tape and jointing
- Carpentry
- Electrical, mechanical and data services
- Plumbing
- Flooring
- Acoustic panels
- Decoration
- Fire stopping
Challenge & solution
The challenge
A live building, and asbestos
The office sits inside a working commercial building, so noise had to be closely controlled, with drilling and other disruptive work done outside normal hours. Access for deliveries and waste was restricted, and the building’s communal areas were already finished to a high standard and needed protecting throughout.
There was also a significant compliance issue: asbestos was present in the subfloor and soffit. On top of that, several items were being supplied directly by the client, each with its own lead time, so the programme had to stay flexible.
Our solution
Careful sequencing and controls
We put the right asbestos procedures and controls in place from the outset, so the work could be carried out safely around it. Deliveries and noisy work were scheduled out of hours wherever possible, and communal areas were protected for the duration.
As principal contractor, we coordinated every trade and kept adjusting the sequence of works around the client’s supply dates while protecting the completion date, with regular communication between Studio Lime, our team and the wider project team. Extra works were added during the programme, but the project still finished on time and within budget, and the snagging items the client expected to raise had already been dealt with before handover.