Our work

Yate Academy Sixth Form

Two classrooms and part of a workshop turned into a sixth form centre in six weeks.

Sector
Education
Project
Demolition & interior fit-out
Location
Yate
Duration
6 weeks
Value
£114,000

Overview

Greenshaw Learning Trust wanted a new sixth form space at Yate Academy that felt lighter, more sociable and more grown-up than a standard classroom, with room for both independent study and group work.

Recommended by Studio Lime Architects, who designed the scheme, Chameleon Group was appointed principal contractor. In six weeks we converted two classrooms and part of the construction workshop into a dedicated sixth form area, with booth seating, bespoke wall-mounted study desks and acoustic treatment.

The project was completed in August 2024, on time, within budget and without incident.

Scope of work

  • Project management
  • Demolition
  • Electrical and data
  • Plumbing and tiling
  • Drylining and plastering
  • Suspended ceilings and acoustic panels
  • Carpentry, including bespoke desks
  • Flooring, decorating and fire stopping
  • Roller shutter
  • Furniture

Challenge & solution

The challenge

A tight programme in a working school

The work had to happen in six weeks, in a building that was still partly in use. Parts of the surrounding school remained open to the public, so the site needed to be properly separated, and every trade on the project needed DBS clearance.

The existing electrics added a further complication. The wiring didn’t relate neatly to the new sixth form area, and working out which distribution boards served which circuits was difficult, because isolating power could also cut supply to other occupied parts of the building. Electrical work couldn’t simply happen when it suited the programme.

Our solution

Contained works and planned isolations

We separated the work area with Heras fencing, a dedicated site entrance and clear signage, and used only DBS-cleared trades. Power isolations were planned and scheduled with the school, so work could go ahead without affecting other areas.

With demolition, electrics, plumbing, ceilings, joinery, decoration and furniture all to fit into six weeks, we ran everything through one coordinated schedule with a single project manager from start to finish. That gave the school one point of contact and kept sequencing and site safety under control. The project was completed on time, within budget and with no incidents.

Next project

Community of Purpose's new office with pink kitchen units, desks and a Powered by Purpose neon sign

Not-for-profit

Community of Purpose

A new office for a Bristol youth charity, designed and fitted out in three weeks.

All projects

Planning a refurbishment in an education setting, or looking to completely transform an existing space?

Whether you’re working with an existing design or need support developing the project from the outset, Chameleon can help bring the different elements together. We’d love to discuss your project.

Get in touch